B alone can finish a piece of work in 15 days, but with A’s help, they complete it in 6 days. In how many days can A alone finish the work?

Show answer & explanation

Correct answer: B

Explanation

B's 1-day work efficiency = 1/15

Combined 1-day work efficiency of A and B = 1/6

Therefore, A's 1-day work efficiency = 1/6 - 1/15

= (5 - 2)/30

= 3/30

= 1/10

So, A alone will complete the work in = 10 days