SSC CHSL 2024 PYQ — Question 59

SSC CHSL - 08 July 2024 - Shift 1 • Quantitative Aptitude • Q59

Antony and Julie can simultaneously complete a work of floor decoration in 15 days and Julie alone in 20 days. In how many days can Antony alone complete the work of floor decoration?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 60.

The time required for Antony and Julie together to complete the work = 15 days

So, they complete 1/15 of the work each day.

The time required for Julie to complete the work = 20 days

So, Julie alone completes 1/20 of the work each day.

Here, (1/15) - (1/20) = 1/60

So, Antony completes 1/60 of the work each day.

Time required for Antony = 1/(1/60) = 60 days

So, Antony alone can complete the work in 60 days.