SSC Selection Post 2025 PYQ — Question 95

SSC Selection Post - Matriculation Level - 29th July 2025 - Shift 1 • Reasoning • Q95

An engineer has given an order to complete the construction before the time but according to the construction it will take more time.
What should he do?

Show answer & explanation

Correct answer: C

Explanation

The correct and practical answer is to "negotiate a revised timeline with stakeholders."

If the construction work is taking longer to complete due to technical or practical reasons, rushing without a plan will compromise the quality and safety of the construction. Therefore, the most responsible step is to inform all stakeholders of the actual situation and negotiate a new, practical timeline.