Aman can do a work in 28 days. What part of the total work can be done by Aman in 8 days?
Show answer & explanation
Correct answer: D
Explanation
The correct answer is Option 4 i.e. 2/7.
Aman can do work in 28 days
One day work = 1/28
Work done by Aman in 8 days = 8/28 = 2/7