Akhil can complete a piece of work in 24 days. Shyam can complete the same piece of work in 12 days. If both of them work together, in how many days can they complete the same piece of work?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is opton 4 i.e. 8 days

Time required for Akhil to complete the work = 24 days

So, Akhil's work per day = 1/24 of the work

Time required for Shyam to complete the work = 12 days

Shyam's work per day = 1/12 of the work

Akhil and Shyam's work per day = (1/24) + (1/12) = 1/8 of the work

Time required for Akhil and Shyam together = 1/(1/8) = 8 days

Therefore, Akhil and Shyam can complete the work together in 8 days.