SSC MTS 2022 PYQ — Question 56

SSC MTS - 19 July 2022 - Shift 3 • Quantitative Aptitude • Q56

A work can be completed by X men in 15 days. 10 more men join them after 3 days. The remaining work is now completed in 8 days. What is the value of X?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e 20

Concept Used :

Total work = Number of men × Number of days.

Given :

X men can do the work in 15 days.

(X + 10) men can do the work in 8 days.

Now the total work done by X men in 15 days = 15X

The work done by X men in 3 days = 3X 

So, the remaining work to be done = 15X - 3X = 12X

Aso, 10 men joined after 3 days, so the number of men is X + 10.

Given that (X + 10) men can complete the remaining work in 8 days

i.e. (X + 10) × 8 = 12X

⇒ 8X + 80 = 12X

⇒ 4X = 80

⇒ X = 20.

Hence the value of X is 20.