A total of 24 men working 7 hours a day can complete a task in 10 days. In how many days will 21 men working 9 hours a day complete the same task?
Show answer & explanation
Correct answer: A
Explanation
The correct answer is option 1 i.e 8 days.
Total work = 24 men × 7 hours/day × 10 days = 1680 man-hours
Now, 21 men working 9 hours/day per day = 189 man-hours/day
Days required = 1680 ÷ 189 = 8 days