SSC CGL 2022 PYQ — Question 73

SSC CGL - 01 Dec 2022 - Shift 3 • Quantitative Aptitude • Q73

A takes 4 times as much time as B or 5 times as much time as C to finish a piece of work. Working together, they can finish the work in 4 days. B can do the work alone in:

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 10 days

Given:

A takes 4 times as much time as B or 5 times as much time as C to finish a piece of work.

Working together, they can finish the work in 4 days.

Concept used:

1. Efficiency (work done per day) of workers is inversely proportional to the time taken by workers to complete a particular task.

2. Total work = Efficiency (Work done per day) × Total time taken

Calculation:

Let the efficiency of A be P.

Hence, the efficiencies of B and C are 4P and 5P respectively.

Total work = 4 × (P + 4P + 5P) = 40P units

Now, B can do the work alone in = 40P/4P = 10 days

B alone can do the work in 10 days.