SSC CPO 2025 PYQ — Question 112

SSC CPO - 12 Dec 2025 - Shift 1 • Quantitative Aptitude • Q112

A small construction firm has 6 workers who can complete a road patching job in 8 days.
If 4 more workers are added, how many days will they take to finish the same work?

Show answer & explanation

Correct answer: D

Explanation

6 employees, 8 days

M₁ × D₁ = M₂ × D₂

6 × 8 = 10 × D₂

48 = 10D₂

D₂ = 48/10 = 4.8 days