SSC GD 2023 PYQ — Question 45

SSC GD Constable (English) - 16 Jan 2023 - Shift 3 • Quantitative Aptitude • Q45

A school manager decides to build a new school building in 40 days. He employs 100 men in the beginning and 100 men after 35 days and completes the construction within the stipulated time. If he had not employed the additional men, how many days behind schedule would the school building have been completed?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 5 days.

Men × time =  Total work

For starting 35 days, total work done by 100 men = 35 × 100 = 3500

He completed the work in 40 days.

So, after 35 days, he employs 100 more men = 5 × 200 = 1000

Total work = 3500 + 1000 = 4500 units

So, if he does not employ extra men then total time = 4500/100 = 45

extra time = 45 - 40 = 5 days