SSC MTS 2019 PYQ — Question 75

SSC MTS Previous Year - 07 August 2019 - Shift 1 • Quantitative Aptitude • Q75

A man can finish a piece of work in 15 days. A woman can complete the same work in 10 days. Both work together for 5 days, then the man leaves. How many days will be taken by the woman to finish the remaining work?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 5/3

Understanding

Application

Calculation

A man and A woman can complete the work in 15 and 10 days respectively.

Suppose,

Total work = LCM of 15 and 10 = 30 units

LCM of 15 and 10 = 5 × 2 × 3 = 30

Efficiency = Work/Time

Efficiency of a man = 2

⇒ 30/15 = 2

Efficiency = Work/Time

Efficiency of a man = 3

⇒ 30/10 = 3

They worked for 5 days together.

So,

Work done = 25 units

Remaining work = 30 – 25 = 5 units

⇒ 5 × (2 + 3) = 25

Remaining work is done by the woman

Time taken by woman = 5/3