SSC CGL 2023 PYQ — Question 75

SSC CGL - 18 July 2023 - Shift 4 • Quantitative Aptitude • Q75

A man and a woman can finish a work together in half the time taken by a woman and a boy together. A boy can finish the work alone in 20 days and 2 women together can finish it in 30 days. In how many days will the work be finished by 4 men?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is Option 2 i.e. 2.14.

Given:

Time taken (Man + Woman) = 1/2 × (Woman + Boy)

Concept used:

If work is constant,

Time is inversely proportional to efficiency

Calculations:

1 Boy completes the work = 20 days

2 woman can complete the work = 30 days

1 woman completes the work = 60 days

Total work (LCM of 30 and 60) = 60 units

Efficiency of a Boy = 60/20 = 3

Efficiency of a woman = 60/60 = 1

We know that,

⇒ Efficiency of (Man + Woman) : Efficiency of (Woman + Boy) = 2 : 1

According to the question;

⇒ 1 unit = 4 units/day

Efficiency of (Man + Woman) = 2 units = 8

Efficiency of man = 8 - 1 = 7 units/day

Required time taken by 4 men = 60/(4 × 7)

⇒ 60/28 = 2.14 days