SSC GD 2023 PYQ — Question 53

SSC GD Constable (English) - 25 Jan 2023 - Shift 3 • Quantitative Aptitude • Q53

A is thrice as good a workman as B. A started the work and they worked together on alternate days and finished the work in 24 days. The number of days taken by A alone to finish the work was:

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 16.

Efficiency of A = 3 × efficiency of B

Efficiency of A/Efficiency of B = 3/1

The efficiency of A and B together = 1 + 3 = 4 units

They work on alternated days.

So, their two days work = 4 unit

2 days = 4 unit

⇒ 24 days = 48 unit = Total work

So, A can alone finish the work = total work/efficiency of A

= 48/3

= 16 days