SSC CHSL 2025 PYQ — Question 54

SSC CHSL - 29 Nov 2025 - Shift 3 • Quantitative Aptitude • Q54

A is capable of completing a task in 10 days, while B can finish the same task in 15 days. A works alone for the first 4 days and is then joined by B. How many total days will it take to complete the entire task?

Show answer & explanation

Correct answer: B

Explanation

Given:

A completes the work in 10 days.

B completes the work in 15 days.

A works alone for the first 4 days.

According to the formula:

Work Rate = 1 / Time

A's work rate per day = 1/10

Work done by A in 4 days = 4/10 = 2/5

Remaining work = 1 − 2/5 = 3/5

Combined work rate of A and B per day

= 1/10 + 1/15

= (3 + 2) / 30

= 5/30

= 1/6

Time = (3/5) ÷ (1/6)

= (3/5) × 6

= 18/5

= 3.6 days

Total time = 4 + 3.6 = 7.6 days