SSC CPO 2022 PYQ — Question 143

SSC CPO - 11 Nov 2022 - Shift 1 • Quantitative Aptitude • Q143

A group of men committed to completing a task in 20 days. The work was completed in 40 days because 5 workers did not come for work. Determine the number of men who originally agreed to do the work.

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 10

Let x be the workers to join initially

According to the question

x × 20 = (x - 5) × 40

20x = 40x - 200

20x = 200

x = 10