SSC CHSL 2025 PYQ — Question 56

SSC CHSL - 18 Nov 2025 - Shift 1 • Quantitative Aptitude • Q56

A does 60% of the work in 18 days. He then calls in B, and they together finish the remaining work in 4 days. How long would B alone take to do the whole work?

Show answer & explanation

Correct answer: D

Explanation

Given:

A completes 60% of the work = 18 days

Remaining work = 40%

A and B together complete the remaining work = 4 days

A's rate = 60% / 18 = 1/30 (work/day)

Remaining work = 40% = 2/5

A + B's rate = (2/5) / 4 = 1/10 (work/day)

B's rate = (A + B) − A = 1/10 − 1/30 = 1/15

B's time to complete the work alone = 1 ÷ (1/15) = 15 days