SSC CGL 2025 PYQ — Question 75

SSC CGL - 14 Oct 2025 - Shift 1 • Quantitative Aptitude • Q75

A contractor hires 10 workers who can complete a task in 16 days. After 4 days, he fires 2 workers. How many more days will the remaining workers take to complete the task?

Show answer & explanation

Correct answer: C

Explanation

Total work = 10 × 16 = 160 man-days

Work done in 4 days = 10 × 4 = 40 man-days

Remaining work = 160 − 40 = 120 man-days

Now man-days = 8

Days = 120 / 8 = 15 days