SSC CHSL 2023 PYQ — Question 68

SSC CHSL 2023 - 03 Aug 2023 - Shift 2 • Quantitative Aptitude • Q68

A contractor employed 69 workers to complete a work in 20 days. How many more workers he should employ to complete the work in 12 days?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 46 workers

Work = Number of workers × Number of days

Initial work = 69 × 20 = 1380 worker-days

Required workers × 12 = 1380

Required workers = 1380 ÷ 12 = 115

Additional workers = 115 − 69 = 46