SSC CGL 2020 PYQ — Question 52

SSC CGL - 7 March 2020 Shift 2 • Quantitative Aptitude • Q52

A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 528

Let 'x' number of males required to complete the remaining work.

⇒ M1D1H1/W1 = M2D2H2/W2

⇒ (187 × 65 × 15)/(3/5) = (x × 10 × 17)/(2/5)

⇒ x  = 13 × 55

⇒ x = 715

Extra men = 715 - 187

⇒ 528 men