A certain number of persons can complete a work in 54 days. If there were 15 persons less, it would take 18 days more for the work to be completed. Initially, the number of persons is:

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 60

Let initially, The number of person = x

According to the question

x × 54 = (x - 15) × (54 + 18)

54x  = 72x - 1080

72x - 54x = 1080

18x = 1080

x = 60 days