SSC Selection Post 2025 PYQ — Question 34

SSC Selection Post - Graduation Level - 29th July 2025 - Shift 3 • Quantitative Aptitude • Q34

A can finish a task in 15 days and B in 20 days. They take a contract for ₹ 18,000. Assisted by C, they complete the job in 6 days. What is C's share of the money?

Show answer & explanation

Correct answer: C

Explanation

A's 1-day work efficiency = 1/15

B's 1-day work efficiency = 1/20

A + B + C complete the work in 6 days.

Therefore, the combined 1-day work efficiency of the three = 1/6

C's 1-day work efficiency = 1/6 − 1/15 − 1/20

= (10 − 4 − 3)/60

= 1/20

Ratio of work = A : B : C = 1/15 : 1/20 : 1/20

= 4 : 3 : 3

Total ratio = 10

C's share = 3/10 × 18000 = ₹5400