SSC CGL - 11 April 2022 - Shift 3 • Quantitative Aptitude • Q58

A can finish a  piece of work in 48 days and B can finish it in 60 days . They work together for 12 days  and then A goes away. In how much time ( in days and hours) will B finshed 25% of the remaining work ?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 8 days 6 hours

Solution :

Let the total work (LCM of 48 and 60) be 240 units.

Efficiency of A = 240/48 = 5 units/day

Efficiency of B = 240/60 = 4 units/day

They worked together for 12 days, so the work done by (A + B) in 12 days = (5 + 4) × 12 = 108 units.

The remaining work = (240 - 108) = 132 units

The time taken by B alone to complete 25 % of the remaining work

⇒ [132 × (25/100)]/4 = 33/4 = 8148\frac{1}{4} days

Hence the required time = 8 days 6 hours