SSC Selection Post 2025 PYQ — Question 42

SSC Selection Post - Matriculation Level - 1st August 2025 - Shift 3 • Quantitative Aptitude • Q42

A can do a work in 12 days, B in 16 days. A works for 3 days, then B joins and they complete the remaining work together.
How many total days did it take to complete the work?

Show answer & explanation

Correct answer: C

Explanation

A's 1-day work efficiency = 1/12

B's 1-day work efficiency = 1/16

Work done by A in 3 days = 3/12 = 1/4

Remaining work = 1 − 1/4 = 3/4

Combined 1-day work efficiency of A and B

= 1/12 + 1/16 = 7/48

Time taken to complete the remaining work -

= (3/4) ÷ (7/48)

= 36/7 days = 5 1/7 days

Total time = 3 + 5 1/7 = 8 1/7 = 8.1days