SSC GD 2025 PYQ — Question 57

SSC GD Const 2025 (English) - 11 Feb 2025 - Shift 3 • Quantitative Aptitude • Q57

A can do a piece of work in 15 days and B can do it in 24 days. If they do the work alternately, in how many days will they finish the work, provided that A begins the work?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 18383\over8.

A’s 1 day work = 1/15

B’s 1 day work = 1/24

Work in 2 days (A + B) = 1/15 + 1/24 = (8 + 5)/120 = 13/120

In 8 days (4 cycles), work done = 4 × 13/120 = 52/120 = 13/30

Remaining work = 1 – 13/30 = 17/30

Next day A works, so days needed = (17/30) ÷ (1/15) = (17/30) × 15 = 8.5 days

Total time = 8 + 0.5 = 8.5 days