SSC GD 2023 PYQ — Question 54

SSC GD Constable (English) - 10 Jan 2023 - Shift 3 • Quantitative Aptitude • Q54

A can do a piece of work in 8 days and B in 24 days. They begin together, but 4 days before the completion of the work, A leaves. Find the number of days taken by A and B to complete the entire work.

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 9 days

The number taken to complete the work = y(x + z)/(x + y)

[Where x and y are the number of days taken by A and B and z is the number of days before A left]

x = 8, y = 24 and z = 4

Days required = 24(8 + 4)/(8 + 24) = 24(12)/32 = 9 days