SSC CPO 2023 PYQ — Question 139

SSC CPO - 03 Oct 2023 - Shift 2 • Quantitative Aptitude • Q139

A can do a piece of work in 8 days, while B can do it in 7 days. If they work at it alternately beginning with A, then in how many days will the work be completed?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 7127 {1{} \over 2}.

Concept used:

Total work done = Efficiency × time

Calculations:

Total work done by A and B (LCM of 8 and 7) = 56 units

Efficiency of A = 56/8 = 7

Efficiency of B = 56/7 = 8

Total work done by A and B if they work alternatively;

⇒ 7 + 8 = 2 days

⇒ 15 units = 2 days

⇒ 45 units = 6 days

⇒ 52 units = 7 days

Now, B will work but will do half of the work.

⇒ 56 units = 7(1/2) days