A can do a piece of work in 18 days. B can do this work in 24 days. A started the work alone. After how many days should B join him, so that the work is finished in 15 days?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is Option 4 i.e. 11 days.

A can do a piece of work in 18 days. B can do this work in 24 days.

A's work in 15 days = 15/18 = 5/6

Remaining work = 1 - 5/6 = 1/6

Remaining work done by B alone in = 1/6 × 24 = 4 days

So, B should join after = 15 - 4 = 11 days