A can do a piece of work in 8 days, while B can do it in 18 days. In how many days will the work be completed if they both work on alternate days starting with B?
Show answer & explanation
Correct answer: A
Explanation
The correct answer is option 1 i.e. 11.
Let the total work be LCM(8 and 18) = 72 units
Amount of work done by A = units
Amount of work done by B = = 4 units
The amount of work completed in 2 days will be 9 + 4 = 13 units
13 units can be completed in 2 days
⇒ 72 units will be completed in = = 11 days