SSC GD 2023 PYQ — Question 43

SSC GD Constable (English) - 24 Jan 2023 - Shift 2 • Quantitative Aptitude • Q43

A can do a piece of work in 4 days, while B can do it in 8 days. If they work on alternate days beginning with A, then in how many days will the work be completed?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is Option 4 i.e. 5.

A can do a piece of work in 4 days, while B can do it in 8 days

L.C.M(4 and 8) = 8

The efficiency of A = 8/4 = 2 units

The efficiency of B = 8/8 = 1 unit

A will work first, work done = 2 unit

Remaining work = 8 - 2 = 6 units

Now, B will work = 1 unit

Remaining work = 6 - 1 = 5 units

Now, A will work = 2 units

Remaining work = 5 - 2 = 3 units

Now, B will work = 1 unit

Remaining work = 3 - 1 = 2 units

Now, A will work = 2 units, and work will be completed

Total time taken to complete the whole work is 5 days