SSC CHSL 2025 PYQ — Question 61

SSC CHSL - 21 Nov 2025 - Shift 3 • Quantitative Aptitude • Q61

A can do a job in 12 days, B can do the same job in 8 days. How long will they take together?

Show answer & explanation

Correct answer: B

Explanation

Given:

A does the work in 12 days

B does the work in 8 days

Together time = (A × B) / (A + B)

Time = (12 × 8) / (12 + 8) = 4.8