SSC CGL 2019 PYQ — Question 100

SSC CGL Tier II Quant - 12/09/2019 • Quantitative Aptitude • Q100

A can do 40% of work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in ?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option ie 4 ie 2 days.

A = 40% → 12 days  → 30%

B = 60% → 15 days  → 25%

30 × 5 = 150

25 × 6 = 150

(5 + 6) × 11 = 1100

(150 - 110) / 4 = 10 units per day

(28 × 1.5) / 21 = 2 days