SSC CGL 2020 PYQ — Question 51

SSC CGL Tier II - Quant - 15 Nov 2020 • Quantitative Aptitude • Q51

A can do 20% of a work in 4 days, B can do 3313\frac{1}{3}% of the same work in 10 days. They worked together for 9 days. C completed the remaining work in 6 days. B and C together will complete 75% of the same work in:

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 10 days

Concept

LCM approach to find total work.

Application

Time taken by A to complete 20% = 4 days

Time Taken by A to complete 100% work = 20 days

 B can do 3313\frac{1}{3}% of the same work = 10 days

Time taken by B to do 100% work = 30 days

Therefore let total work = 60 units (LCM of 30 and 20)

A's efficiency = 3 units

B's efficieny = 2 units

Total work done by A and B in 9 days = 9 x ( 3+ 2)

= 45 units

Work Left = 60 - 45 = 15 days

It is completed by C in 6 days

C's efficient = 15 / 6 = 2.5 units

B & C will complete the 75 % of the work = (60 x 75 ) / 100 x 4.5 = 10 days