SSC CGL 2022 PYQ — Question 63

SSC CGL - 18 April 2022 - Shift 2 • Quantitative Aptitude • Q63

A can complete work in 25 days and B can complete the same work in 20 days. They started the work together but B left after 4 days and A continued to work. In how many days will the entire work be completed?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 20

Time in which A can complete the work = 25 days

Time in which B can complete the work = 20 days

Time for which B worked = 4 days

Total work = L.C.M of 20 and 25 = 100 units

Amount of work done by A in one day = 100/25 = 4 units

Amount of work done by B in one day = 100/20 = 5 units

Total work done by both of them in four days = (4 × 4 + 5 × 4) = 16 + 20 = 36

Remaining work = 100 - 36 = 64 units

Remaining work is done by A alone in = 64/4 = 16 days

Total time taken to complete the work = 16 + 4 = 20 days