A can complete some work in 35 days and B can complete the same work in 15 days. They worked together for 8 days, then B left work. In how many days will A alone complete 60% of the remaining work?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 5.

Time taken by A to complete the whole work = 35 days

Time taken by B to complete the whole work = 15 days

Hence total work = LCM of (35 and 15) = 105 units

Now,

Efficiency of A = 105/35 = 3 units

Efficiency of B =105/15 = 7 units

They work together for 8 days,

thus work done in 8 days = Combined efficiency of A and B × 8

⇒ (3 + 7) × 8 = 80 units

Now work left after 8 days = 105 - 80 = 25 units

Time taken by A to complete 60% of remaining work = (60/100 × 25)/3 = 15/3 = 5 days