A can complete one-fourth of a work in 2 days and B can complete three-fifth of the same work in 6 days. In how many days will they complete the work if they work together?
Show answer & explanation
Correct answer: C
Explanation
The correct answer is option 3 i.e. .
Time taken by A to complete the work = 8 days
Time taken by B to complete the work = 10 days
Work completed in 1 days by A and B together = (1/8) + (1/10)
⇒ 9/40
Time taken by A and B together to complete the work = 40/9 =