SSC CHSL 2025 PYQ — Question 70

SSC CHSL - 19 Nov 2025 - Shift 2 • Quantitative Aptitude • Q70

A can complete a work in 8 days, while B can do it in 16 days. How many days will they take together?

Show answer & explanation

Correct answer: B

Explanation

Given:

A works alone = 8 days

B works alone = 16 days

A's work rate = 1/8

B's work rate = 1/16

A + B's work rate = 1/8 + 1/16 = 3/16

Time = 1 ÷ (3/16) = 5⅓ days