SSC CGL 2021 PYQ — Question 62

SSC CGL - 18 Aug 2021 - Shift 3 • Quantitative Aptitude • Q62

A can complete a work in 60 days. B is 25% more efficient than A. They work together for 15 days. C alone completes the remaining work in 14 days. B and C together will complete 58\frac{5}{8}th part of the original work in:

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 12 days.

Let the efficiency of A = 4 units/ day

Total work = 4 × 60 = 240 units

The efficiency of B = 125% of 4 = 5 units/day

Both A and B work for 15 days

Work done by A and B in 15 days = 15 × 9 = 135 units

Remaining work = 240 - 135 = 105 units

The efficiency of C = 105/14 = 7.5 units/day

5/8 of the work = 5/8 × 240 = 150 units

Time taken by B and C to finish 150 units of work = 150/12.5 = 12 days