SSC CHSL 2025 PYQ — Question 61

SSC CHSL - 14 Nov 2025 - Shift 1 • Quantitative Aptitude • Q61

A can complete a work in 30 days. How much work will he complete in 6 days?

Show answer & explanation

Correct answer: C

Explanation

Given:

A completes the work = 30 days

Time = 6 days

Work done = 6 / 30 = 1/5