SSC Selection Post 2025 PYQ — Question 41

SSC Selection Post - Matriculation Level - 26th July 2025 - Shift 1 • Quantitative Aptitude • Q41

A can complete a work in 12 days and B can complete it in 8 days. How long will they take together?

Show answer & explanation

Correct answer: A

Explanation

A's 1-day work efficiency = 1/12

B's 1-day work efficiency = 1/8

Combined 1-day work efficiency of both = 1/12 + 1/8

= (2 + 3)/24

= 5/24

Therefore, time taken to complete the work = 24/5 days

= 4.8 days