SSC CHSL 2024 PYQ — Question 54

SSC CHSL - 04 July 2024 - Shift 2 • Quantitative Aptitude • Q54

A can complete a piece of work in 20 days and B can complete the same work in 10 days. With the help of C, working together they completed the work in 5 days. The number of days in which C alone can complete the work is:

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 20.

A can complete the work in 20 days,

so Rate of A =1/20 work per day

B can complete the work in 10 days,

so Rate of B = 1/10 work per day

Combined rate = 1/5 ​work per day

The combined rate of A, B, and C is the sum of their individual rates:

⇒ Rate of A + Rate of B + Rate of C = 1/5

⇒ 1/20 + 1/10 + Rate of C = 1/5

⇒ Rate of C = 1/5 - 1/20 - 1/10 = (4 - 1 - 2)/20 = 1/20

then C alone can complete the work =

Time for C = 1/Rate of C = 20 days