SSC CGL 2023 PYQ — Question 65

SSC CGL - 26 Jul 2023 - Shift 2 • Quantitative Aptitude • Q65

A can complete a piece of work alone in 120 days, while A and B, working together, can complete this piece of work in 72 days. In how many days can B, working alone, complete this piece of work?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 180.

We know,

Work = Efficiency × time

Now,

Total work (LCM of 120 and 72) = 360 units

⇒ Efficiency of A = 360/120 = 3

⇒ Efficiency of (A + B) = 360/72 = 5

Efficiency of B = 5 - 3 = 2

Hence, the required number of days taken by B to do the work alone = 360/2 = 180