A can complete a job in 15 days and B in 20 days. They work together for 5 days. How much work is left?

Show answer & explanation

Correct answer: B

Explanation

Given:

A does the work in 15 days

B does the work in 20 days

They both work together for 5 days

A's rate = 1/15

B's rate = 1/20

Together's rate = 1/15 + 1/20 = 7/60

Work done in 5 days = 5 × 7/60 = 7/12

Remaining work = 1 − 7/12 = 5/12