A can complete 2/5th of the work in 12 days, and B can complete 7/8th of the same work in 21 days. Find the number of days in which A and B together can complete the work.

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 40/3 days

Given that

A can complete 2/5th of the work in 12 days

A can complete the whole work in 12 × (5/2) = 30 days

B can complete 7/8th of the same work in 21 days

B can complete the whole work in 21 × (8/7) = 24 days

Total work = LCM (30, 24) = 120 days

The efficiency of A = 120/30 = 4

The efficiency of B = 120/24 = 5

Hence, A and B together can complete the work in 120/(4 + 5) = 120/9 = 40/3 days