SSC CGL 2018 PYQ — Question 31

SSC CGL Tier II Quant - 21/02/2018 • Quantitative Aptitude • Q31


 

A, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 6

Let the total work be 36 units

Efficiancy of(A + B) = 4 - 1 = 3

Time taken by (A + B) to complete 50% work = 18/3 = 6 days