SSC Selection Post 2023 PYQ — Question 67

SSC Selection Post - Matriculation Level - 27 June 2023 - Shift 1 • Quantitative Aptitude • Q67

A, B and C can separately complete a work in 20, 25 and 30 days, respectively. If A works on the first day alone, B on second day alone and C on the third day alone, and this sequence goes on further, in how many days will the entire work be finished?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 244154\over15.

Work in 3 days (A + B + C) = 1/20 ​+ 1/25 ​+ 1/30

⇒ 15/300 + 12/300 + 10/300 = 37/300

After 8 cycles (24 days) = 8 × 37/300 = 296/300

Remaining work = 1 − 296/300 = 4/300 = 1/75

Time = Work/Rate ​ = (1/​75)/(1/20) ​​ = 20/75 ​= 4/15​ day

Total time = 24 + 4/15 ​= 364/15 ​= 244154\over15​​ days