SSC GD 2023 PYQ — Question 48

SSC GD Constable (English) - 12 Jan 2023 - Shift 4 • Quantitative Aptitude • Q48

A, B, and C can do a piece of work in 8, 4, and 16 days respectively. How many days will A take to complete the entire work if A is assisted by B and C both on every second day?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is Option 1 i.e. 26/7 days.

A, B, and C can do a piece of work in 8, 4, and 16 days respectively

L.C.M(8, 4, and 16) = 16

The efficiency of A = 16/8 = 2 units

The efficiency of B = 16/4 = 4 units

The efficiency of C = 16/16 = 1 units

Only A will work on the first day = 2 units

A will be assisted by B and C both on the second day = 2 + 4 + 1 = 7 units

Work done in 2 days = 9 units

Work done by A on the third day = 2 units

Work done in 3 days = 11 units

Remaining work = 16 - 11 = 5 units

Time taken by A = 3573\frac{5}{7} = 26/7 days