SSC CHSL 2019 PYQ — Question 68

SSC CHSL - 4th July 2019 - Shift 3 • Quantitative Aptitude • Q68

A, B and C can complete a piece of work in 4, 28 and 56 days respectively. Working together, they can complete the same work in how many days?

Show answer & explanation

Correct answer: D

Explanation

Correct Answer is option 4 i.e. 56/17

Understanding

Application

A, B and C can complete the work in 4, 28 and 56 days respectively.

Total work = 56 units [LCM of 4, 28 and 56]

Efficiency of A = 56/4 = 14

Efficiency of B = 56/28 = 2

Efficiency of C = 56/56 = 1

 

Time in which they will complete the work together = 56/(14 + 2 + 1) = 56/17 days