SSC GD 2025 PYQ — Question 57

SSC GD Const 2025 (English) - 10 Feb 2025 - Shift 2 • Quantitative Aptitude • Q57

A, B and C can complete a piece of work in 12, 20 and 15 days, respectively. A, B and C will complete the work while working on alternate days. C works on the 1st day, B works on the 2nd day and A works on the 3rd day and so on. In how many days will the work get complete?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 15 .

A's 1-day work = 1/12

B's 1-day work = 1/20

C's 1-day work = 1/15

Work pattern: Day 1 = C, Day 2 = B, Day 3 = A → repeats every 3 days.

Work in 3 days = C + B + A

= 1/15 + 1/20 + 1/12

LCM = 60 → (4 + 3 + 5)/60 = 12/60 = 1/5

So, in 3 days → 1/5 of work done

Total work = 1

Time = 3 × 5 = 15 days