SSC CGL 2023 PYQ — Question 70

SSC CGL - 20 July 2023 - Shift 3 • Quantitative Aptitude • Q70

A and B working together can finish a piece of work in 8 days while B alone can do it in 24 days. In how many days can A alone finish the work?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 12.

Given:

A and B working together can finish a piece of work in 8 days

B alone can do it in 24 days

Calculations:

Total work (LCM of 8, 24) = 24 units

The efficiency of A and B = 24/8 = 3

Efficiency of B = 24/24 = 1

So, the efficiency of A = 3 - 1 = 2

Hence, Required time taken by A = 24/2 = 12 days