SSC GD 2025 PYQ — Question 50

SSC GD Const 2025 (English) - 12 Feb 2025 - Shift 3 • Quantitative Aptitude • Q50

A and B working separately can finish the work in 18 days and 24 days, respectively. A begins the work and works for two consecutive days, while B works on the 3rd day. This pattern is continued till the work is completed. In how many days will the work be completed?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 19121\over2.

LCM(18, 24) = 72

The efficiency of A = 72/18 = 4 units

The efficiency of B = 72/24 = 3 units

Work done in three days = 4 + 4 + 3 = 11 units

Work done in 18 days = 66 units

Remaining = 72 - 66 = 6 units

Day 19 (A) does 4 units, Remaining = 2 units

Day 20 (A) needs 2/4 = 0.5 day

Total time = 18 + 1 + 0.5 = 19.5 days